Effect of project time control on the delivery of the Ayimensah housing project by Krane construction

dc.contributor.authorLaryea, Evans Quaye
dc.contributor.author
dc.date.accessioned2021-07-13T14:26:05Z
dc.date.accessioned2023-04-19T04:46:41Z
dc.date.available2021-07-13T14:26:05Z
dc.date.available2023-04-19T04:46:41Z
dc.date.issued2021-07-13
dc.descriptionA thesis submitted to the Department of Building Technology, College of Art and Built Environment, Kwame Nkrumah University of Science and Technology, Kumasi in partial fulfillment of the requirement for the Degree of Master of Science in Project Management.en_US
dc.description.abstractThis research selected the Ayi Mensah Housing project to review the time control practices on the project and objectives included examining the time control practices, identifying challenges with their implementation and proposing best practices for project time control. The literature review unearthed relevant past research on the subject matter and formed the bases for the research instrument that was targeted at staff members working on the Ayi Mensah Housing project for data collection. A descriptive research design was adopted, and also applied a mixed method approach towards data collection and analysis. Based on the analysis of the data collected, in line with the literature findings, it was concluded that time control practices on the Ayi Mensah Housing project were in line with recommendations for industry and practice, including definition of activities, sequencing, estimation of resources and duration and finally scheduling. The selection of tools used for time control purposes were also in line with industry specifications, including most common ones such as Precedence Network Diagrams, Critical Path Network, Templates and Critical Path Analysis. The research also concluded that computer software were heavily relied on for project scheduling, and included the use of Microsoft Project and Microsoft Excel. In terms of the identified challenges to implementing time control practices, it was concluded that the most significant for the Ayi Mensah Housing project included scope changes, improper risk analysis and management, impossible deadlines, estimating task duration and assigning resources. Best practices identified for successful time control was for the strengthening of the existing practices, such as the use of standardized templates, precedence and critical networks and adequate allocation for risk. It was also recommended that project managers build their capacity, commit resources and time to planning and companies adopt time control policiesen_US
dc.description.sponsorshipKNUSTen_US
dc.identifier.urihttps://ir.knust.edu.gh/handle/123456789/14380
dc.language.isoen_USen_US
dc.subjectTime controlen_US
dc.subjectProject managementen_US
dc.titleEffect of project time control on the delivery of the Ayimensah housing project by Krane constructionen_US
dc.typeThesisen_US
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Laryea Evans Quaye.pdf
Size:
1.9 MB
Format:
Adobe Portable Document Format
Description:
License bundle
Now showing 1 - 2 of 2
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.73 KB
Format:
Item-specific license agreed to upon submission
Description:
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed to upon submission
Description: