An analysis of productivity and cost efficiency of underground labour at George Capendel Shaft of Ashanti Goldfields Corporation (Ghana) Limited

dc.contributor.authorFrimpong, Mensah
dc.date.accessioned2012-04-03T21:45:32Z
dc.date.accessioned2023-04-19T19:58:03Z
dc.date.available2012-04-03T21:45:32Z
dc.date.available2023-04-19T19:58:03Z
dc.date.issued1990-09-03
dc.descriptionA thesis submitted to the Board of Postgraduate Studies, Kwame Nkrumah University of Science and Technology, Kumasi, in partial fulfilment of the requirements for the award of Postgraduate Diploma in Mining Engineering, 1990en_US
dc.description.abstractThe treatise analyses the possibilities of increasing productivity at optimum cost. The study revealed that labour motivation at AGC is quite low. Job-centered style of supervision, machine downtime poor environmental conditions and labour unrest are among the factors hindering productivity. Productivity is analysed terms of tons or advance per man-shift. Production efficiency is the ratio of actual to the programmed productivity whereas cost efficiency is the ratio of forecast cost to the actual. The mean actual productivities of the various stopes were; for cut – and – fill (conventional) stopes (2 t/m-s), cut – and – fill (machinised) stopes (2.5 t/m-s), sublevel are 3. t/m-s, 8 t/m-s, 3.2 t/m-s respectively, and 2.5 t/m-s for shrinkage stopes. At development ends, mean productivities were 0.61 feet/man-shift for raises and 0.875 feet/man-shift for lateral development The percent-age contribution of the operating cost of mining by the various cost centers are ; stoping cost (36.56%) , slope preparation cost ( 13. 18%) -. slope development cost (26. 96%) and 2 3% for the working cost.. The study also revealed a decline in performance of AGC in terms of cost from 1980/81 to date.en_US
dc.description.sponsorshipKNUSTen_US
dc.identifier.urihttps://ir.knust.edu.gh/handle/123456789/3395
dc.language.isoenen_US
dc.relation.ispartofseries1758;
dc.titleAn analysis of productivity and cost efficiency of underground labour at George Capendel Shaft of Ashanti Goldfields Corporation (Ghana) Limiteden_US
dc.typeThesisen_US
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
KNUST Library.pdf
Size:
7.09 KB
Format:
Adobe Portable Document Format
Description:
License bundle
Now showing 1 - 2 of 2
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.73 KB
Format:
Item-specific license agreed to upon submission
Description:
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed to upon submission
Description:
Collections