Key Causes Of Delay In Construction Projects – Views Of Ghanaian D3k3 And A3b3 Contractors

dc.contributor.authorFobi, Daniel Yaw
dc.date.accessioned2015-02-20T11:53:20Z
dc.date.accessioned2023-04-21T02:48:29Z
dc.date.available2015-02-20T11:53:20Z
dc.date.available2023-04-21T02:48:29Z
dc.date.issued2015-02-20
dc.descriptionA Thesis Submitted to the Department of Building Technology, Kwame Nkrumah University of Science and Technology in partial fulfillment of the requirements for the award of a degree of Master of Science in Construction Management, 2014en_US
dc.description.abstractDelay is among the key challenges faced in the course of construction project implementation. Construction project delay is a globalproblem inproject delivery.Several attempts by researchers’ and project professionals to tackle this problem have not yielded sufficient positive results. This hasgreat negative impact in terms of cost and risk in construction projectswith its related effects on contracting parties.The aim of this study wasto identify the key causes of construction project delays in the view of small scale Ghanaian contractors.Hence, in achieving the aim of the study the following specific objectives were advanced, one, to identify the most important causesof delay and two, to identify solutionto the causes of delays. Thestudy adopted a quantitative structured questionnaire survey.Respondents were selected by the quota sampling technique. Out of Seventy one (71) questionnaires distributed,Sixty Four (64) wereretrieved from respondents representingNinety percent (90).Relative Importance Index and Factor Analysis were used to analyze objective one and two data respectively.The study revealed that, the main causes of delaysare:Clients inadequate financial resources, delays in honouring payment certificates for work done, underestimation of the project duration, poor communication between contracting parties and complexity for developers to access bank credit. In concluding, the following measures were espoused for effective construction delivery: initial proper planning, establishing appropriate communication media and sticking to payment schedules agreed by all the contracting parties.  en_US
dc.description.sponsorshipKNUSTen_US
dc.identifier.urihttps://ir.knust.edu.gh/handle/123456789/6865
dc.language.isoenen_US
dc.subjectCausesen_US
dc.subjectDelayen_US
dc.subjectConstructionen_US
dc.subjectProjectsen_US
dc.subjectGhanaen_US
dc.subjectContractorsen_US
dc.titleKey Causes Of Delay In Construction Projects – Views Of Ghanaian D3k3 And A3b3 Contractorsen_US
dc.typeThesisen_US
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
FOBI YAW DANIEL_masters.pdf
Size:
1.44 MB
Format:
Adobe Portable Document Format
Description:
Full Thesis
License bundle
Now showing 1 - 2 of 2
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.73 KB
Format:
Item-specific license agreed to upon submission
Description:
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed to upon submission
Description: