Factors influencing construction projects delays in national vocation training institute NVTI

dc.contributor.authorOppong, Joseph Kwabena
dc.contributor.author
dc.date.accessioned2021-06-15T14:05:33Z
dc.date.accessioned2023-04-19T03:25:00Z
dc.date.available2021-06-15T14:05:33Z
dc.date.available2023-04-19T03:25:00Z
dc.date.issued2021-06-15
dc.descriptionThe thesis submitted to the Department of Construction Technology and Management in partial fulfillment of the requirements for the Degree of Master of Science en_US
dc.description.abstractConstruction projects in National Vocational Training Institute (NVTI) have experienced several challenges with the strong challenge of delays of the projects. Numerous factors influenced this issue of construction project delays, and the aim of the study was to explore the causative factors influencing construction projects delays in NVTI. The objectives were: to identify factors which influence construction project delays in NVTI, to provide solutions / mitigation measures to reduce construction projects delays in NVTI. The study made use of quantitative approach of enquiry through survey questionnaires. A sum total of seventy – two (72) questionnaires were administered and sixty – two (62) responses were retrieved from NVTI Staff representing the client, Contractors and Consultants (project managers, architects, quantity surveyors, works engineers) who have previously executed NVTI construction projects indicating a high response rate of 86%. The analysis of the data gathered was done using descriptive statistics (frequencies, percentages) and mean score ranking. The study revealed that, there were sixteen (16) factors which influence construction project delays but ten (10) of them were identified as the key ones and include; Lack of adequate budgetary support, Inadequate funding allocation, Time and Cost overrun Lack of effective communication between parties, Slow in decision making. Design errors and omissions / Poorly defined scope/ specification of work Contractor‘s financial difficulties / Use of obsolete plant and equipment, Poor project management practices on a project site, inadequate experience of consultants Lack of vehicles for monitoring and supervision of works. It was recommended that the government should make adequate funds available before the start of every contract, contractors should practice proper site management whereas the consultants should also do due diligence to avoid errors and put in place good project management practices.en_US
dc.description.sponsorshipKNUSTen_US
dc.identifier.urihttps://ir.knust.edu.gh/handle/123456789/13946
dc.language.isoen_USen_US
dc.subjectDelayen_US
dc.subjectFactorsen_US
dc.subjectFactorsen_US
dc.subjectNVTI,en_US
dc.titleFactors influencing construction projects delays in national vocation training institute NVTIen_US
dc.typeThesisen_US
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Joseph Kwabena Oppong_masters.pdf
Size:
1007.23 KB
Format:
Adobe Portable Document Format
Description:
Full Thesis
License bundle
Now showing 1 - 2 of 2
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.73 KB
Format:
Item-specific license agreed to upon submission
Description:
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed to upon submission
Description: