Assessment of the challenges for project closure practices in Ghana: a case study of the shopping malls in Ghana

dc.contributor.authorSegbedzi, Walter
dc.date.accessioned2025-03-21T11:34:10Z
dc.date.available2025-03-21T11:34:10Z
dc.date.issued2019-11
dc.descriptionA thesis submitted to the department of Construction Technology and Management, Kwame Nkrumah University of Science and Technology, Kumasi, in partial fulfilment of the requirements for the award degree of Master of Science in Construction Management
dc.description.abstractThe study sought to investigate the effectiveness of the project closure practices used in the Ghanaian construction industry. To achieve the aim, the study set out three objectives: to examine construction project closure practices in the Ghanaian construction industry; to evaluate challenges associated with project closure practices in the Ghanaian construction industry; and to establish strategies to mitigate the outlined challenges of project closure practices in the Ghanaian construction industry. The study employed the quantitative method of research. Questionnaires were developed and distributed among fifty-nine (59) respondents comprising of construction project professionals from the construction of four of shopping malls in Ghana namely the Accra Mall, the West Hills Mall, the Kumasi City Mall and the Takoradi Mall. Fourteen (14) belonged to the employee of owner/client, twenty (20) were employees of contractor while the remaining twenty-five (25) belonged to employee of consultant of construction projects. Data collected were analyzed by means of Relative Importance Index (RII) and the mean-score. The study revealed that the general practice of closing the project consisted of contractual and administrative closure practices. Majority of eighty percent (80%) practiced the contractual closure practices. Further, the study identified eleven (11) factors of challenges related to the construction project closure practices which “contractor related activities” was ranked as the highest challenge hampering the effectiveness of construction project closure practice. It was also revealed by the study that, effective communication and co-ordination should be exercised during construction by all stakeholders as that was ranked as the highest strategy to foster effective construction project closure practice. The study recommends that administrative closure practices should also be practiced frequently by the construction project managers just as they practice the contractual closure practice. Also, provision of “certificate of beneficial occupancy to the owner to use the facility” must be encouraged to be done for all construction project closures. Lastly, the study recommends the importance of a close out schedule, that, it is agreed to by all stakeholders so that everyone’s requirements can be met. There is the need to circulate this early (efficient communication) so each one can work towards this and ease the handing over process at the end.
dc.description.sponsorshipKNUST
dc.identifier.urihttps://ir.knust.edu.gh/handle/123456789/16420
dc.language.isoen
dc.publisherKNUST
dc.titleAssessment of the challenges for project closure practices in Ghana: a case study of the shopping malls in Ghana
dc.typeThesis
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Walter_ Segbedzi_Msc.pdf
Size:
1.42 MB
Format:
Adobe Portable Document Format
Description:
License bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed to upon submission
Description: